Completion of Preljina-Pozega Highway Moved to End-June 2024 – Contract Extended for Companies Which Supervise Works
Source: eKapija
Tuesday, 28.02.2023.
12:15
Comments
Illustration (Photo: sumanamul15/pixabay.com)
As said, an additional period of engagement of 16 months is required, because the works over which expert supervision is done were not finished within the planned deadline.
The agreement has now been extended until June 30, 2024, for the consortium of companies which was hired for this job in August 2019, when the construction of the section started (Gradjevinski institut Centralna putna laboratorija doo Veternik, Makspro doo Zemun, Adomne doo Novi Sad and ABA professional doo Beograd).
The price of the job has been raised accordingly, from RSD 966.8 million to RSD 1.4 billion.
Let us remind that the works on the Preljina-Pozega section, according to the agreement with the contractor, the Chinese company CCCC, were supposed to be completed by the end of this year.
That was repeated by the minister of construction of Serbia, Goran Vesic, 10 days ago, while visiting the site of the construction of the Laz Tunnel on this section.
He said that the tunnel tubes were supposed to be bored through by the end of April.
– The boring through of the second tunnel on the route, Munjino Brdo, is expected by the end of the year, so that the Chinese partners would try to fulfill what we’ve agreed, to complete this highway section by the end of the year – Vesic said.
Take a look at our info-map Construction of Highways and Fast Roads in Serbia and Region.
B. P.
Companies:
Ministarstvo građevinarstva, saobraćaja i infrastrukture Republike Srbije
Centralna putna laboratorija d.o.o. Veternik
Makspro d.o.o. Beograd
Adomne doo Novi Sad
Aba professional doo Beograd
China Communications Construction Company ltd Beograd
Tags:
Ministry of Construction Transport and Infrastructure
Građevinski institut Centralna putna laboratorija doo Veternik
Makspro doo Zemun
Adomne doo Novi Sad
ABA professional doo Beograd
CCCC
Goran Vesić
highway E 763
Preljina Požega section
highway construction
Laz Tunnel
Munjino brdo Tunnel
supervision of the construction of Preljina Požega highway section
Comments
Your comment
Most Important News
Full information is available only to commercial users-subscribers and it is necessary to log in.
Follow the news, tenders, grants, legal regulations and reports on our portal.
Registracija na eKapiji vam omogućava pristup potpunim informacijama i dnevnom biltenu
Naš dnevni ekonomski bilten će stizati na vašu mejl adresu krajem svakog radnog dana. Bilteni su personalizovani prema interesovanjima svakog korisnika zasebno,
uz konsultacije sa našim ekspertima.